Port of Everett Central Marina Phase 4 Dredging & G Dock
Date
9/15/2019-2/15/2020
Location
Everett, WA
Contract
$3,066,000
Project Summary
The Central Marina Improvements will demolish 45,000 square feet of covered moorage, dredge 30,000 cy, install 500 LF of new concrete docks with galvanized piling, and relocate existing boathouses.
Rob Pate, Superintendent & Rod Gowdy, Operations Manager